We were sub-contracted to build the shafts and the tunnels by the main contractor - Aoki/Soletanche JV - for Contract 105 on the Jubilee Line Extension Project. The project consisted of the following elements.
- 5 km - 4400mm diameter running tunnels using 4 No. Kawasaki EPB TBM's
- 2 No hand excavated 140 metre long station tunnels constructed in compressed air of 7m diameter cast iron segments.
- The sinking of 6 No. shafts of both diaphragm and segmental construction all approx. 14m diameter at 30 metre deep.